top of page

Stealth Broadband Fiber & Grants Projects & Updates
Nebraska NUSF-131 Projects
Antelope County
Fiber-to-the-Home Internet service for all residents in the yellow blocks pictured below, featuring speeds up to 1 Gbps
Progress:
Engineering - complete
Permitting - estimated completion Spring 2025
Construction - estimated completion Summer 2025
Splicing and testing - estimated completion Summer 2025
Customer installations - estimated start date Fall 2025



Boone County
Fiber-to-the-Home Internet service for all residents in the yellow blocks pictured below, featuring speeds up to 1 Gbps
Progress:
Engineering - complete
Permitting - complete
Construction - estimated completion Spring 2025
Splicing and testing - estimated completion Spring 2025
Customer installations - estimated start date Spring 2025

Madison County
Fiber-to-the-Home Internet service for all residents in the yellow blocks pictured below, featuring speeds up to 1 Gbps

Progress:
Engineering - complete
Permitting - estimated completion Summer 2025
Construction - estimated completion Fall 2025
Splicing and testing - estimated completion Fall 2025
Customer installations - estimated start date Winter 2025/2026



Platte County Central
Fiber-to-the-Home Internet service for all residents in the yellow blocks pictured below, featuring speeds up to 1 Gbps
Progress:
Engineering - complete
Permitting - estimated completion Winter 2024/2025
Construction - estimated completion Spring 2025
Splicing and testing - estimated completion Spring 2025
Customer installations - estimated start date Summer 2025

Platte County East
Fiber-to-the-Home Internet service for all residents in the yellow blocks pictured below, featuring speeds up to 1 Gbps
Progress:
Engineering - complete
Permitting - complete
Construction - complete
Splicing and testing - Winter 2024/2025
Customer installations - starting NOW

Platte County North
Fiber-to-the-Home Internet service for all residents in the yellow blocks pictured below, featuring speeds up to 1 Gbps

Progress:
Engineering - complete
Permitting - estimated completion Spring 2025
Construction - estimated completion Summer 2025
Splicing and testing - estimated completion Summer 2025
Customer installations - estimated start date Fall 2025
Platte County South
Fiber-to-the-Home Internet service for all residents in the yellow blocks pictured below, featuring speeds up to 1 Gbps
Progress:
Engineering - complete
Permitting - estimated completion Spring 2025
Construction - estimated completion Summer 2025
Splicing and testing - estimated completion Summer 2025
Customer installations - estimated start Summer 2025

bottom of page