Projects & Updates
Koliha Grain Leg - Wireless Internet Expansion, Rural Colfax County
Wireless Internet service will be available to all residents within the highlighted project area, with speeds up to 200 Mbps.

Progress:
Engineering - complete
Installation - scheduled to begin 10/06/23
Customer installations - ready for installations 10/09/23
Clarkson Fiber to the Home
Fiber to the Home for all residents within the Clarkson city limits, featuring speeds up to 1 Gbps
Progress:
Engineering - complete
Permitting - complete
Construction - complete
Splicing and testing - in progress, estimated completion 10/20/23
Customer installations - ready for installations 10/16/23

Platte Center Fiber to the Home
Fiber to the Home for all residents within the Platte Center city limits, featuring speeds up to 1 Gbps

Progress:
Engineering - complete
Permitting - complete
Construction - in progress, estimated completion 11/03/23
Splicing and testing - scheduled to begin 11/24/23
Customer installations - estimated start date 11/27/23
Platte County Central Unserved - Nebraska CPF Project
Fiber to the Home for all residents within the highlighted project area below, featuring speeds up to 1 Gbps
Progress:
Engineering - in progress, estimated completion 10/13/23
Permitting - estimated completion 11/03/23
Construction - estimated completion Spring 2024
Splicing and testing - estimated completion Spring 2024
Customer installations - estimated start date Spring 2024
Platte County East Unserved - Nebraska CPF Project
Fiber to the Home for all residents within the highlighted project area below, featuring speeds up to 1 Gbps
Progress:
Engineering - estimated completion Winter 2024
Permitting - estimated completion Winter 2024
Construction - estimated completion Summer 2024
Splicing and testing - estimated completion Summer 2024
Customer installations - estimated start date Summer 2024
Platte County North Unserved - Nebraska CPF Project
Fiber to the Home for all residents within the highlighted project area below, featuring speeds up to 1 Gbps
Progress:
Engineering - in progress, estimated completion Winter 2024
Permitting - estimated completion Winter 2024
Construction - estimated completion Spring 2024
Splicing and testing - estimated completion Spring 2024
Customer installations - estimated start date Spring 2024
Platte County North Underserved - Nebraska CPF Project
Fiber to the Home for all residents within the highlighted project area below, featuring speeds up to 1 Gbps
Progress:
Engineering - in progress, estimated completion Winter 2024
Permitting - estimated completion Winter 2024
Construction - estimated completion Spring 2024
Splicing and testing - estimated completion Spring 2024
Customer installations - estimated start date Spring 2024
Platte County South Underserved - Nebraska CPF Project
Fiber to the Home for all residents within the highlighted project area below, featuring speeds up to 1 Gbps
Progress:
Engineering - in progress, estimated completion Winter 2024
Permitting - estimated completion Winter 2024
Construction - estimated completion Summer 2024
Splicing and testing - estimated completion Summer 2024
Customer installations - estimated start date Summer 2024

Colfax County East Unserved - Nebraska CPF Project
Fiber to the Home for all residents within the highlighted project area below, featuring speeds up to 1 Gbps
Progress:
Engineering - estimated completion Spring 2024
Permitting - estimated completion Spring 2024
Construction - estimated completion Fall 2024
Splicing and testing - estimated completion Fall 2024
Customer installations - estimated start date Fall 2024