Stealth Broadband Fiber & Grants Projects & Updates
Platte County Central Unserved -Â Nebraska CPF-2023 Project
The Stealth Broadband service area is shaded in yellow below.
Fiber-to-the-Home Internet service for residents along the green and orange fiber routes below.
Green = Complete
Orange = In Progress
Featuring speeds up to 1 Gbps
Progress:
Engineering - complete
Permitting - complete
Construction -Â partially complete - estimated completion Spring 2024
Splicing and testing - partially complete - estimated completion Spring 2024
Customer installations - NOW in completed areas - estimated start date Spring 2024
Â
Platte County East Unserved -Â Nebraska CPF-2023 Project
The Stealth Broadband area is shaded in teal below.
Fiber-to-the-Home Internet service for all residents along the green and orange fiber routes below.
Green = Complete
Orange = In Progress
Featuring speeds up to 1 Gbps
Progress:
Engineering - complete
Permitting - estimated completion Summer 2024
Construction - estimated completion Fall 2024
Splicing and testing - estimated completion Fall 2024
Customer installations - estimated start date Fall 2024
Â
Platte County North Unserved -Â Nebraska CPF-2023 Project
The Stealth Broadband area is shaded in purple below.
Fiber-to-the-Home Internet service for all residents along the green and orange fiber routes below.
Green = Complete
Orange = In Progress
Featuring speeds up to 1 Gbps
Progress:
Engineering - complete
Permitting - partially complete - estimated completion Spring 2024
Construction - partially complete - estimated completion Spring 2024
Splicing and testing - partially complete -Â estimated completion Spring 2024
Customer installations - NOW in completed areas - estimated completion date Summer 2024
Â
Platte County North Underserved -Â Nebraska CPF-2023 Project
The Stealth Broadband area is shaded in purple below.
Fiber-to-the-Home Internet service for all residents along the green and orange fiber routes below.
Green = Complete
Orange = In Progress
Featuring speeds up to 1 Gbps
Progress:
Engineering - complete
Permitting - partially complete - estimated completion Spring 2024
Construction - partially complete - estimated completion Spring 2024
Splicing and testing - partially complete -Â estimated completion Spring 2024
Customer installations - NOW in completed areas - estimated completion date Summer 2024